A Florida couple signed a $2.775 million contract for a custom home and paid a $257,500 deposit, but construction never began; five years later, an appeals court reversed a $126,624.63 damages award. A Florida couple who paid $257,500 towards a $2.775 million custom home in Tampa, only for the construction project to collapse before work began, have seen a damages award of $126,624.63 reversed by an appeals court.The Sixth District Court of Appeal of Florida ruled on Wednesday that the couple’s claims of fraudulent misrepresentation and violations of consumer protection law against the construction company’s owners should have been referred to arbitration under the agreement they signed.The decision overturns the amended final judgment entered by an Orange County trial court against Susan Zimmerman and Tom Zimmerman, who owned Madison Construction. The case has been sent back for proceedings to enforce the contract’s arbitration provision.The dispute began in 2020, when Carlos R. Diez-Arguelles and his wife, Maria Tejedor, approached Madison Construction to design and build a home on a waterfront property in Tampa. $257,500 home deposit became a legal battle The couple first signed a design agreement with Madison in July 2020, paying a fee that would later be credited towards construction costs. They entered into a construction contract in November that year, setting the total project price at $2.775 million.The agreement required a non-refundable deposit of 10 per cent. After accounting for the design fee, the couple paid $257,500 on the day they signed the construction contract.Madison continued working on the project into mid-2021, with Tejedor exchanging emails about changes to the initial design. In July that year, Tom Zimmerman told the couple to expect updated plans, a revised payment schedule and new pricing through a DocuSign document.The couple disputed the changes and refused to sign the updated documents. Over the following two months, Diez-Arguelles sent letters demanding an account of the money paid and asking the company either to begin construction under the original agreement or return the deposit.Madison subsequently declared the couple in default and sent them a cheque for $150,875.37, representing the amount it calculated was refundable under the contract.The dispute later reached court. Diez-Arguelles alleged that the Zimmermans had misrepresented their professional qualifications, including claims that they were licensed contractors. He also alleged that they failed to disclose that Madison’s licensed contractor, Garland Knight, would not personally supervise the project, and that the company’s in-house design professional was not a licensed architect.The Zimmermans denied making the alleged misrepresentations. Why the appeals court overturned the damages award The Orange County trial court initially ruled in favour of Diez-Arguelles on his fraudulent misrepresentation claim. In an amended final judgment, it also found the Zimmermans liable under the Florida Deceptive and Unfair Trade Practices Act (FDUTPA) and awarded $126,624.63 in damages.The Zimmermans challenged the decision, arguing, among other things, that the construction contract required disputes to go through mediation and arbitration rather than court proceedings.The appeals court agreed that the trial court had wrongly rejected their request to enforce that provision.In its opinion, the panel noted that the contract covered disputes connected to the construction agreement, dealings between the owners and contractor, and alleged representations made by the contractor or its representatives.It also found that the Zimmermans, although not signatories to the agreement in their personal capacity, were Madison’s agents and were entitled to enforce the arbitration clause as intended third-party beneficiaries.The judges said the couple’s allegations were directly connected to the construction contract because they concerned the money paid towards the project, the company’s failure to return the remaining deposit and representations made during the contractual relationship.The court therefore reversed the judgment against the Zimmermans on the fraud and FDUTPA claims and remanded the case for enforcement of the arbitration provision.The ruling did not establish that the alleged misrepresentations were false or that the Zimmermans were free from liability. Instead, it determined that the claims must be addressed through the agreed dispute-resolution process.The appeals court also upheld the trial court’s decision finding Knight not liable on those claims. Its rulings in favour of all three defendants on the separate theft, statutory civil theft and conversion claims remained unchanged.The decision was issued by the Sixth District Court of Appeal on November 25, 2026, with Chief Judge Traver and Judge Brownlee concurring. Source link Post Views: 2 Post navigation US customs open a parcel from UAE headed to an Illinois home and find 440 fake Cartier, Tiffany and Bulgari jewellery pieces with a potential retail value of $2.4 million | World News 17-year-old on Australia’s Gold Coast feared her nan’s stories would be lost, so she built a website where people record messages for loved ones to receive on birthdays and Christmases after they die